Road construction on GRE-35-5.63 eastbound, until Aug 31, 2026 — 16.4 miles from New Carlisle
Construction of an interchange at the routes’ intersection between Xenia and Beavercreek.
ODOT reports road construction on GRE-35-5.63 eastbound, about 16.4 miles from New Carlisle. ODOT
What the record shows
Traffic is being maintained on U.S. 35; however, westbound U.S. 35 has been shifted to the north and is now being diverted by way of the interchange ramps to and from Trebein Road. A traffic signal at the inter… Reported March 1, 2023. Expected to clear by August 31, 2026. ODOT
Context
By the numbers
Assembled mechanically from the source filing and The Lantern's own record database — no AI-written prose. Every figure above appears verbatim in the cited record, which is linked on this page. ODOT
Sources
The source filing
| Road | GRE-35-5.63 |
|---|---|
| Direction | eastbound |
| Category | Road Work - Planned |
| Description | Construction of an interchange at the routes’ intersection between Xenia and Beavercreek. Traffic is being maintained on U.S. 35; however, westbound U.S. 35 has been shifted to the north and is now being diverted by way of the interchange ramps to and from Trebein Road. A traffic signal at the intersection of Trebein Road and the westbound on/off ramp is in stop-and-go operation. Additional, intermittent lane restrictions and traffic changes will be in effect in the work zone. |
| Distance from New Carlisle | 16.4 miles |
| Reported | March 1, 2023, 7:00 a.m. |
| Expected end | August 31, 2026, 7:59 p.m. |
Published by Ohio Department of Transportation (OHGO). This is the agency's public filing as The Lantern received it, shown with its fields named in plain English.